Civil Construction Sydney

Carry out Civil Construction in Sydney CBD, City Zone Development Project. Brown Field Site, Estimate approximately 5.6 klms of duct line installed and 8 Vaults completed. Substantial amount of night works due to council and RTA constraints.

Works included:

  • Installation of 16 & 24 way duct lines throughout the Sydney CBD.
  • Construction of Cable Vaults throughout the Sydney CBD, many of which are located in the centre of major intersections.
  • Removal of existing brick vaults and expansion of those vaults. Demolition works around live HV and Fibre optic cables.
  • Extensive cable hauling throughout the Sydney CBD.
  • Removal of ACM conduits throughout the Sydney CBD and replacement with PVC duct lines.
  • Traffic management for Cable installation and associated civil works within the Sydney CDB region.
  • Permanent restoration on all the associated works and area.

This project was completed for Ausgrid.

Send an enquiry